GRAVEL HILL & DUNYEATS

The Port of Poole Programme consists of six transport schemes to improve access into and around the Port of Poole. The investment helps drive local economic growth and bring an anticipated £500 million of leveraged private investment into the area.

Project Status - Completed

  • Start Date: April 2016
  • End Date: June 2017
  • Local Growth Fund allocation: £3,356,000
  • Awarded to: BCP Council
  • Part of the Port of Poole Programme

Project Summary

A £3,356,000 million Local Growth Fund investment at Gravel Hill & Dunyeats on the A349, the main link road into the Port of Poole and the town centre from the A31.

Work covered:

  • Stabilising and strengthening embankments
  • Increasing capacity for motor vehicles at the Queen Anne junction
  • Improving facilities for pedestrians and cyclists

Outputs:

Mildren Construction was appointed as contactor and they carried out the improvement works to strengthen Gravel Hill embankment and address drainage. This involved:

  • The major earthworks to widen and stabilise the embankment.
  • Refurbishment of the large culvert (man-made piped structure) which carries Blackwater Stream under the road.
  • Improvements to the road's surface drainage.
  • Widening the existing footway to construct the shared pedestrian/cycle lane to provide the missing cycle link connecting Merley to Poole Town Centre.

 

View the End of Project Report here.